Construction Timeline
The work will be divided into three project packages.
Package One
Alamo Heights High School – construction May 2024 to August 2026
Central Office/Learning Center – construction June 2026 to April 2027
Excel Academy/Connects – construction May 2027 to December 2027
Package Two
Robbins campus (located next to Tennis Center/Natatorium and current home of Excel and 09 Academies)
Softball Field and Accessory Buildings – construction October 2024 to September 2025
Tennis Improvements- construction January 2025 to December 2025
Baseball Improvements- construction January 2025 to December 2025
Robbins Building Removal and New Parking Lot – construction January 2028 to June 2028
Cambridge – construction January 2025 to August 2026
Woodridge – construction June 2025 to August 2026
Plant Services – construction September 2025 to March 2026
Package Three
Howard Early Childhood Center – construction May 2026 to July 2027
Alamo Heights Junior School – construction April 2027 to June 2028
All dates slated for campus construction projects are subject to change due to factors like weather.